TORRINGTON, Wyo. (RELEASE) August 7, 2019--The Goshen Irrigation District, along with the Gering-Fort Laramie Irrigation District releases its weekly update for the emergency tunnel collapse and canal repair project to keep landowners and public aware of its ongoing repair efforts which began on July 27, 2019. The project is progressing and moving ahead as expected with still many unknowns of the inner tunnel damage and its stability. 

Canal Repair and Restoration Project
Within days of the collapse, efforts to rebuild the main canal have been ongoing to stabilize the floor, banks, and restore the canal to its original holding capacity. The bank sides have been rebuilt up to around 8 feet high with final target height of 15-20 feet. The canal rebuild is going as planned with no delays or issues.  

Tunnel Repairs
The tunnel repairs and inner damage assessment remain ongoing. The tunnel crew is continuing the process of drilling holes in the tunnel ceiling and examining the concrete depth and thickness. Ribbing structures/supports are then being installed inside the tunnel to ensure stability and safety. Once the work area is secure, a highly specialized foaming grout is pumped into the ceiling where it expands and fills any holes, voids or spaces above the tunnel.  The tunnel crew secured the tunnel to approximately 625 feet from the entrance. They have encountered the dirt and debris from the first and smallest collapse in the tunnel. Crews are now walling up the tunnel to prevent any cave-ins or dirt collapses. The wall will allow the crew to excavate the dirt and push the wall forward while moving dirt out of the tunnel. The crew will continue to secure the inner tunnel and move towards the second and largest collapsed area. While the repair efforts are progressing, the unknown nature of damage to the walls and ceiling has yet to be fully examined and keeps the project in a “design as you go” scenario.    


Sinkhole Excavation and Stability Efforts
Since last week, additional crews and machinery focused on excavating the sinkhole from above ground to the area of the tunnel breach. What was once a hole, has expanded to a massive area of dirt extraction and stabilization.  The tunnel ceiling is approximately 150 feet deep from the surface. As the excavation crew nears the tunnel ceiling, large trench boxes will be installed in a few days to surround the collapse tunnel ceiling, to minimize dirt fill into the tunnel, and allow repair workers to explore the damaged and collapsed ceiling from above.   

LANDOWNER MEETING AUG. 12th – 2pm
A second informational meeting for landowners and the public has been set for August 12th at 2pm at the EWC Auditorium. The meeting will feature resources and speakers from UWYO/UNL Extension partnership efforts, an update from the GID Commissioners and any other additional information and updates. Additional meeting information and updates can be found at GoshenIrrigation.com or via its Facebook page.  

TIMELINE AND WATER RESTORATION
As noted above, this project consists of three full-time ongoing efforts to repair, maintain and secure the areas damaged by the massive collapse and breach. The project is moving ahead as planned without delays, but GID stresses the public and landowners will be informed of any 3 time or water restoration dates when they become available and certain. Any reports or updates beyond GID’s official posts and statements should be not be relied on without any guarantee of certainty or accuracy.  

Share this post

Submit to DeliciousSubmit to DiggSubmit to FacebookSubmit to Google PlusSubmit to StumbleuponSubmit to TechnoratiSubmit to TwitterSubmit to LinkedIn
Category: regional news

Most Recent News

  • REGIONAL NEWS

    image description
    Emergency Canal & Tunnel News

    TORRINGTON, Wyo. (RELEASE) August 7, 2019--The Goshen Irrigation District, along with the Gering-Fort Laramie Irrigation District releases its weekly update for the emergency tunnel collapse and canal repair project to keep landowners and public aware of its ongoing repair efforts which began on July 27, 2019. The project is progressing and moving ahead as expected with still many unknowns of the inner tunnel damage and its stability. 

     

    read more 
  • REGIONAL NEWS

    image description
    Fatal Crash South of Wheatland

    WHEATLAND, Wyo. (RELEASE) August 5, 2019--On July 30, 2019, a fatal crash occurred around milepost 73 on Interstate 25 south of Wheatland, Wyoming.  Around 7:49 a.m., Wyoming Highway Patrol troopers were dispatched to the area for a one-vehicle rollover.
     
    A 2003 Buick Century was traveling northbound on Interstate 25 when the vehicle drifted into the median and in between the north and south bridge decks of Interstate 25 at the Highway 34 interchange.  The Buick overturned and came to a rest on Highway 34.      

     

    read more 
  • REGIONAL NEWS

    image description
    Crop Insurance Coverage

    GOSHEN COUNTY, Wyo. (RELEASE) August 1, 2019--

    By Jessica Groskopf, Regional Agricultural Economist & Cory Walters, Assistant Professor, University of Nebraska-Lincoln
     

    As repairs continue on the tunnel that collapsed on the Goshen/Gering-Fort Laramie Canal, unanswered questions remain about whether crop insurance will cover crop losses stemming from the loss of irrigation water.
         

    Crop Insurance provides protection against “unavoidable, naturally occurring events.”  Due to the complexity of the Goshen/Gering-Fort Laramie situation, it is unknown if crop insurance will cover crop loss.
      

     

    read more 
  • REGIONAL NEWS

    image description
    Meeting for Landowners and Public

    TORRINGTON, Wyo. July 24, 2019--Hundreds of people filled the Eastern Wyoming College auditorium for a public meeting that was held at 2 pm on Wednesday, concerning the collapse of the Ft. Laramie tunnel and canal. Even though the auditorium was filled with mixed emotions including fear and sadness, people had positive demeanors. Everyone remains optimistic.  A man led a prayer for farmers, families, workers, and representatives.  


    A company out of Houston has been hired and is in the process of building pipe for the replacement of the collapsed tunnel. GID Commissioners Secretary/Treasurer, Shawn Booth, explained that once the pipe is completed, they will haul it to Goshen County to begin the installation.  Members of the GID Board are trying to be optimistic in hoping that there is a time table of the end of August for irrigators to see a water supply again.

     

    read more